List of job executed FOR RLA
CHATTISGARH State Electricity Board
4x210 MW, HASDEO THERMAL POWER STATION,
KORBA WEST
completed electrical system for unit-ii
- Power Transformers
- Bus ducts
- LT transformers
- Unit control protection system
- HT switchgears
- LT switchgears
- HT motors
- LT motors
- HT and LT cables
- ESP Electrical
- Internal Coal handling electrical systems
- External Coal handling electrical systems.
- DC system
- EOT Cranes.
- DG sets.
- Plant lighting, Cabling, Earthing & Lightning system.
DURATION OF JOB: 30 Days
punjab STATe electricity board
4x210 MW, GGSSTP POWER STATION,
ROPAR
completed electrical system for unit-ii
- Power Transformers
- Bus ducts
- LT transformers
- Unit control protection system
- HT switchgears
- LT switchgears
- HT motors
- LT motors
- HT and LT cables
- ESP Electrical
- Internal Coal handling electrical systems
- External Coal handling electrical systems.
- DC system
- EOT Cranes
- DG sets
- Plant lighting, Cabling,Earthing & Lightning system
DURATION OF JOB: 15 Days
hindustan zinc ltd
132 /11 KV Sub-station – Hindustan Zinc Ltd – Debari Dist
Udaipur, Rajasthan
completed electrical system for 2 bay of 132 KV substation.
- Power transformer
- Current transformer
- Breakers
- Isolators
- Lighting arresters
- Control and relay panels
- OLTC and RTCC
- Potential transformers
- Earthing system
DURATION OF JOB: 15 Days
UTTAR PRADESH Rajya Vidyut Utpadan Nigam Ltd.
1322 MW THERMAL POWER STATION
OBRA, UTTAR PRADESH
completed electrical system for 5X200MW “B” TPS, UNITS 9-13
- Power Transformers (2 No.s )
- HT Motors
- Pentograph Isolators
- Lightning Arresters
- Intercom system
DURATION OF JOB: 7 Days
Zuari Cement LIMITED
Yerraguntla – Andhra pradesh
completed electrical system for CPP
DURATION OF JOB: 3 Days
|